Update: Scott Stadium Expansion Carl Smith Center

VIRGINIASPORTSDOTCOM
VIRGINIASPORTSDOTCOM

VIRGINIASPORTSDOTCOM

Aug. 7, 2000

  • Scott Stadium Expansion Photo Gallery

    The month of July saw the pace of the finish and site work increase significantly and many areas of the stadium are nearing completion. The State Fire Marshal inspections on 5, 6 and 27 July were completed with no significant issues raised. Preparations for the final State Fire Marshal's visits on 3, 4 and 7 August are now under way with the State Code Officials due on 8 August. Major work continued on finishing the President's Box/Press Box, Suites, Bryant Hall Level's 1 and 2, the Parking Garage, and the East and West site work.

    Furniture installations in Bryant Hall Level 2 started on 21 July with the arrival of 3 tractor-trailers, and all of the furniture installations will be completed by 4 August. The Parking Garage work continued with the paving of the ground level, caulking and sealing of the top 2 decks, the installation of the lights on all levels, and the installation of the sprinkler and ventilation systems on the ground level. There will be testing of the many new systems throughout August and we will advise the neighborhood if any will affect the areas around the stadium.

    Please do not hesitate to call the office at 243-8710 if you have any questions on the Project's progress or the upcoming schedule of work during the month of August.